Invincible Reclaim Paste Backfill System

Completed for Gold Fields in Western Australia, the Invincible Reclaim Paste Backfill System showcases MineFill’s EPC delivery of a modular greenfield paste plant.

Project Details

Client:

Gold Fields

Location:

Western Australia

Scope:

Engineering, Procurement and Construction

Duration:

12 Months

Budget:

AU$11M

Project Overview

A modular greenfield paste plant built for gravity delivery

In 2024, MineFill Services completed the design and construction of a greenfield paste plant solution for Gold Fields in Western Australia. Built on a reclaimed salt lake foundation, the project utilised a modular plant design with container silos and a MineFill feeder-conveyor to generate paste output for gravity delivery to underground stopes.

Paste output
0 ³/h
Project duration
0 months

AU$11M

Project budget

MineFill delivered a modular paste plant solution designed for high-output gravity delivery in challenging site conditions.

Project Details

The project required the delivery of a greenfield paste plant on a reclaimed salt lake foundation, creating specific site conditions that needed to be addressed through practical engineering and construction planning.

The system also needed to support high paste output while maintaining a modular and efficient plant configuration suited to the project requirements.

MineFill delivered the engineering, procurement and construction of a modular paste plant solution incorporating container silos and a MineFill feeder-conveyor system.
The plant was designed to generate 190m³/h paste output, with material delivered to underground stopes via gravity.

The completed Invincible Reclaim Paste Backfill System demonstrates MineFill’s ability to deliver practical greenfield paste plant solutions for major mining clients.
Through modular design and focused EPC delivery, MineFill provided a paste backfill system aligned to the operational requirements of the site.

More Projects

Explore more MineFill projects

Australia

Delivered for Alkane Resources, the Tomingley Paste System showcases MineFill’s integrated approach from early studies to complete EPC delivery.

Australia

Completed for Newmont Limited in Western Australia, the Telfer Rey Paste Backfill System showcases MineFill’s EPC delivery of a reclaim tailings paste plant integrated into an existing hydraulic fill operation.