Wassa Project

Completed for Golden Star Resources in Ghana, the Wassa Project highlights MineFill’s specialist backfill testing and technical review capabilities to improve paste performance and operational outcomes.

Project Details

Client:

Golden Star Resources

Location:

Ghana

Scope:

Paste Strength Review and Testing Campaign

Duration:

6 Months

Budget:

US$90K

Project Overview

Improving paste performance through detailed testing and technical review

In 2021, MineFill completed a review of both current site data and previous strength testwork for the Wassa Project in Ghana. The assessment identified no conclusive reason for the significantly lower strengths being achieved onsite.

Following the initial review, MineFill undertook a detailed strength testing campaign to further investigate paste performance and support operational improvements. The results assisted site personnel in improving paste quality assurance and quality control processes.

2021

Project completed

Project duration
0 months

US$90K

Project budget

MineFill delivered a detailed testing and review program to identify performance issues and support improved paste QA/QC outcomes.

Project Details

The operation was experiencing significantly lower paste strengths than expected, despite existing site data and previous testwork being available. Understanding the cause of the performance discrepancy was critical to improving confidence in the backfill process.

MineFill conducted a comprehensive review of available operational data and historical strength testing results. Following this assessment, a more detailed strength testing campaign was undertaken to further investigate paste behaviour and identify opportunities for improvement.

The testing program provided valuable technical insights into paste performance and supported improvements to site QA/QC procedures. The project demonstrates MineFill’s ability to combine laboratory testing expertise with practical operational support to help mining operations optimise backfill performance.

More Projects

Explore more MineFill projects

Australia

Completed for Gold Fields in Western Australia, the Invincible Reclaim Paste Backfill System showcases MineFill’s EPC delivery of a modular greenfield paste plant.

Australia

Delivered for Alkane Resources, the Tomingley Paste System showcases MineFill’s integrated approach from early studies to complete EPC delivery.